Briggs and Stratton SimpliPhi 6.6

Briggs and Stratton SimpliPhi 6.6

Project Documentation
Take a photograph of the battery stack(s)

BASCO Integration Guide
A maximum of 6 stacks can be connected in a single system.
Per NFPA 855, a maximum of 40kWh in utility spaces or  basements and 80kWh in garages our outdoor locations.
Systems larger than 80kwh should consult local AHJ for site requirements.

Required Tools

Materials Not Included
Floor Mount and Base Mount are ordered separately and fasteners are not included.

Floor mount base not intended for seismic zones.

Do not install the Battery Temperature Sensor. The PHI Batteries require no temperature compensation.

Provided Components
Each stack must have a Briggs & Stratton controller at the top and a Briggs & Stratton floor or wall mount bracket base on the bottom. Each stack must be installed at least 3 feet away from each other.

Structural Attachment Required
The installed wall hardware must be attached to concrete or finished studs. Drywall anchors can be used in addition to, but cannot replace, the structural hardware. 
Don’t let your stationary battery system accidentally become a mobile battery system!

Alert
Reserve Capacity of 20%
To optimize the PHI batteries’ and overall system’s performance and life, SimpliPhi Power recommends programming the equipment settings for an 80% maximum Depth of Discharge (DoD). Maintaining the PHI battery at this DoD qualifies it for the 10-year / 10,000 cycle Warranty level. SimpliPhi warranties the PHI battery for fewer cycles at greater DoD levels: 90% DoD is correlated with a 5,000-cycle Warranty and 100%
DoD correlates with a 3,500-cycle Warranty. 

Installation Angle
The SimpliPHI 6.6 battery is designed to be vertically mounted. The battery system must be installed upright with
less than 1° tilt from vertical. 

Do not install the battery system upside down, on its back, side, more than 1° tilt from vertical, or on tilted walls. When installing the SimpliPHI 6.6 battery on uneven or sloped surfaces, it might be necessary to install shims between the floor and the bottom of the foot.

Floor Mount Base Installation
Floor Mount Base Installation
(ordered separately)

For non-seismic zone floor mount installations, install on
concrete floors with anchors using 1/4"-5/16” fasteners to >2” deep or wood floors with 1/4"-5/16” lag screws to full thread engagement through the subfloor.

Use a level to determine if the floor is level and that the wall is plumb. If the floor is not level, shims can be used to create a level surface.

Use a measuring tape to determine the hole positions for the floor mount base according to Figure 2 below. Mark the positions using a marker or pencil.

NOTE: Use the provided positioning guide to determine spacing from the wall to the floor mount base. The back holes of the floor mount base must be ~1⅝” from the wall, not
including the baseboards.
Floor Mount Base Installation Part 2
2. Pre-drill holes as required for fasteners to be used. For concrete, use of a hammer drill is recommended.

3. Remove any dust from in and around the holes and verify the distances between anchor points after drilling. If the
holes are incorrectly positioned, mark and drill again leaving enough space to not interfere with the existing holes.

4. If required, follow the manufacturer's instructions when placing anchors.
Floor Mount Base Option
(ordered separately)

Place the floor mount base on the floor aligned with the holes. Hand tighten the 4 bolts with appropriate locking
and flat washers. See Figure 3. Make sure that the floor mount base is level. Adjust with shims if necessary.

Tighten the bolts to manufacturer torque specifications. Do a second check to make sure that the floor mount base is still level.
Wall Mount Base Option
(ordered separately)

The SimpliPHI 6.6 Battery wall mount base is designed to secure up to three (3) SimpliPHI 6.6 Batteries to a load bearing surface. The wall mount base can be mounted directly to a wall, or it can be arranged on strut channels for ease of positioning (fastening hardware is not included). The wall mount base must be mounted into two (2) load bearing beams, studs, or a solid material, with appropriate fasteners. The wall mount base is designed to hold up to three SimpliPHI 6.6 Modules and one Controller with a combined weight of up to 435 pounds.

Warning
Warning
Do not anchor to drywall alone. The system must be anchored to wood studs, cement blocks or concrete.

Check with the local AHJ regarding required mounting height above the floor.

When the battery is installed on the wall, do not place any objects below or on top of the battery.
Stud Attachment
For Stud attachment: Following Figure 4 below, use a measuring tape to determine the hole positions for the wall mount base and mark the positions using a marker
or pencil. Space the holes according to the stud spacing and put 2 bolts/lags per stud for a total of 4 bolts/lags in 2
studs.

Wood Studs: lag screws of 1/4"-5/16” diameter and >3” length.

Metal Studs: 1/4"-5/16” bolt diameter toggle bolts
Wall Mount Bracket Installation - Wood or Metal Studs Part 2
Use the appropriate drill for the material to pre-drill holes on the wall in the specified
positions.

If the holes are incorrectly positioned, mark and drill again. Leave enough space to not interfere with the existing holes.

 Tighten the bolts by hand, with appropriate lock washers and fender washers.

Make sure that the wall mount base is level. Adjust if necessary
For Concrete Wall Attachment
For Concrete Wall attachment: Use all 12 holes
specified in Figure 5.

Concrete: Anchors with 1/4"-5/16” bolt diameter and
>1” insertion into concrete
Concrete Wall Attachment Part 2
Use the appropriate drill for the material to pre-drill holes on the wall in the specified
positions.

If the holes are incorrectly positioned, mark and drill again. Leave enough space to not interfere with the existing holes.

 Tighten the bolts by hand, with appropriate lock
washers and fender washers.

Make sure that the wall mount base is level. Adjust if necessary
For Floor Mount Installations Against Wall
Measure the centerline of the floor mount base (14 ¼” from the edge) and mark the center line on the floor mount base.

Place the positioning guide between the wall and the
floor mount base as shown in Figure 8. 

Align the notch
with the centerline. 

Use a level to draw a vertical line on the wall, aligned with the top of the positioning guide.
Floor Mount Base Part 2
Align the bottom of the Vertical Spacer with the line
drawn in the steps above. Fasten the Vertical Spacer,
as shown in Figure 9, so it does not move.
For wall mount instructions
Using the provided M6 x 5/16” screw, attach the Vertical
Spacer to the Wall Mount Base as shown in Figure 10.
For all installations
Using the provided M6 x 5/16” screw, attach the Horizontal bracket to the Vertical Spacer as shown in Figure 11

Check that the Horizontal Retainer is level. Mark the locations on the wall where bolts for the Horizontal
Retainer will be installed as shown in Figure 12 (for studs) or 13 (for concrete).
3. Attach the Horizontal Retainer to the wall using appropriate hardware for the wall material. Use
appropriate fender washers as well
Fasten Wood or Concrete wall support bracket
Wood Studs: 1/4"-5/16” diameter wood screws, 2” or
longer

Metal Studs: 1/4"-5/16” diameter toggle bolts.

Concrete: 1/4"-5/16” diameter bolts in anchors installed
at least 1” into concrete.
Adding Additional Batteries
For each additional battery (up to three) in the stack, screw in the vertical spacer to the last horizontal retainer installed. Repeat steps 1 through 3 for each horizontal retainer, as shown in Figure 14 (for studs) or 15 (for concrete).

Battery and Controller Installation
Each SimpliPHI 6.6 battery weighs 140 lb. Have at least two (2) people lift the battery. Follow proper lifting form to minimize the chance of injury.

Remove shoulder screws
Remove the four rear shoulder screws as shown in Figure 16

Set and secure first battery
Install the first battery module on the base by aligning the bracket guides on the side of the battery with the tabs on the battery mount. Attach the battery module to the mount using the provided M4 x 10mm screws. See Figures 17 and 18.

Reinstall shoulder screws 
Reinstall the rear shoulder screws into the battery through the slot on the wall retainer, as shown in Figure 19.

Set and secure additional batteries
If applicable, repeat steps 1-3 to install the second battery module on top of the first and the third battery on top of the second. See Figure 20.

Install controller head unit
Once all batteries are stacked and properly attached to each other, Install the controller on top of the last battery by aligning the bracket guides on the side of
the Controller with the tabs on the battery. Attach the controller to the battery using the provided M4 x 10mm screws. See Figure 21.
Conduit Connection Sealing
Use a #1 Phillips screwdriver to remove the six (6) M3 x 8mm screws from the top plate and four (4) M3 x 8mm screws for the side plate from surrounding the electrical compartment of the Controller. See Figure 22.

Choose the appropriately sized conduit, up to 2” trade size maximum, for your cables per local AHJ and NEC installation requirements.

Punch out the Side Plate
Mark and punch the conduit entry point in the side plate. See Figure 23.

NOTE: Using the top plate for conduit or wiring accessibility will void the IP65 outdoor rating.

Reinstall the side plate with fittings
DO NOT INSTALL THE TOP PLATE YET.

Install the conduit chase nipple or appropriate outdoor rated fitting onto the side plate. See Figure 24.

Reinstall the side plate using the four (4) M3 x 8mm screws and a #1 Phillips screwdriver. 


NOTE: Using the top plate for conduit or wiring accessibility will void the IP65 outdoor rating.
Electrical Wiring Installation
DO NOT INSTALL THE TOP PLATE YET.

Install the conduit chase nipple or appropriate outdoor rated fitting onto the side plate. See Figure 24.

Reinstall the side plate using the four (4) M3 x 8mm screws and a #1 Phillips screwdriver. 


NOTE: Using the top plate for conduit or wiring accessibility will void the IP65 outdoor rating.
External Charger
Only use a Briggs & Stratton approved LFP charger if ancillary charging is required at any point before or during installation, testing or troubleshooting. Failure to use a Briggs & Stratton approved LFP charger will damage the SimpliPHI Batteries and violate the terms of the Warranty.

Single Stack Wiring
When connecting a single stack to a single charge controlling device with a built-in disconnect for the batteries, no external disconnect is necessary. If there is not a disconnect built-in to the charge controlling device, a disconnect must be installed between the battery stack and charge controlling device. 

This disconnect must be sized to the device with the lower rated current. If the disconnect sizing requirements are uncertain, refer to local AHJ and NEC guidelines. When connecting a single stack to multiple devices, a disconnect is required between the battery stack and the charge controlling devices.

Recommended OCPD
Remember each battery port on the Sol-Ark 15K is rated for 200A. To get a full 275A out of the Sol-Ark 15K, use both battery ports and ensure cable run is suitably rated for full amperage. 
Parallel Stack Installation
Up to 6 SimpliPHI 6.6 Battery Stacks can be wired in parallel from the terminals of the Controller to a properly sized combining busbar. Between each stack and the busbar, a DC single-pole overcurrent protection device is required (double-pole is recommended). 

Follow local AHJ and NEC DC overcurrent protection device sizing requirements. The table above lists the recommended overcurrent protection device size per NEC 2023. 

Make sure that all cable lengths from each stack are identical in length and gauge to maintain equal resistance across the stacks.


Alert
Caution
Identical wire lengths and identical wire gauges from each SimpliPHI Battery in a SimpliPHI Battery System is a critical feature of parallel power storage systems that must be adhered to. Failure to properly wire the SimpliPHI Batteries in parallel can damage the system and will violate the terms of the Warranty

Electrical Wiring Instructions
Turn ON the SimpliPHI 6.6 BESS (hold power button on the Controller until all LEDs on batteries and Controller are ON.)

2. Measure the voltage at the Controller power terminals. 

NOTE: If the SimpliPHI Battery’s voltage has dropped to a voltage below the inverter’s minimum starting voltage requirement, then the battery will need to be charged using an external charger. SimpliPHI batteries have a very low self-discharge rate and typically do not require ancillary charging,but an extended period in storage can cause the batteries to
discharge.

Electrical Wiring Instructions Pt 2
3. Turn OFF the SimpliPHI 6.6 BESS. (Hold the power button on the Controller until the Controller LEDs are OFF.)

4.Measure the voltage at the Controller power terminals. The voltage will measure <5 VDC if the system is off.

Ground Cable Installation
A grounding position is provided to comply with local AHJ and NEC grounding requirements. Ground as required. 

Terminate the ground cable (sized to local AHJ and NEC requirements) with a 1/4” closed-end Ring Terminal.

Cover the exposed wire between the lug and wire sheath with heat shrink.

Attach the ground wire with the ¼” ring terminal with the M5x10mm screw provided, as shown in Figure 26.

Torque to 1.7 ft-lb maximum (20 in-lb)

Power Cable Installation
Terminate the Negative and Positive cables (sized to local AHJ and NEC requirements) with a ⅜” closed-end Ring Terminal. Cover the exposed wire between the lug and wire sheath with heat shrink.

Do not use power tools or impact drivers to tighten the terminal hardware. This can result in damage to the terminal and will violate the terms of the Warranty.

Attach the Positive cable with the 3/8” ring terminal with the provided M10x25mm bolt, to the RED terminal as shown in Figures 27 and 28. Torque to 15 ft-lbs (180 in- lbs) maximum.

Single Stack Installation with Sol-Ark Residential 
Inverters and EnergyTrak (Figure 30):
1. Connect a CAT5 (or greater) cable to the “CAN” RJ-45 port on the Controller and to the provided Sol-Ark Battery Communications Adapter.
2. Connect the provided Sol-Ark Battery Communications Adapter into the CAN connector on the Sol-Ark inverter.
3. Connect a CAT5 (or greater) cable between the “RS485” RJ-45 port on the Controller and the provided EnergyTrak Gateway Battery Communications Adapter.
4. Connect the provided EnergyTrak Gateway Communications Adapter into the CAN connector on the EnergyTrak gateway.

Multi-Stack Installations
For installations containing multiple stacks, the Controllers must be connected to each other via CAT5 (or greater) cables. In all configurations, all RJ-45 connectors must be occupied by a Battery CAN terminator, CAT5 connection to an adjacent battery stack, or a provided Battery Communications Adapter.
1. Connect the first stack to the inverter or EnergyTrak gateway from the port labeled CAN using the correct adapter provided.
2. Connect Cat5 (or greater) cable to the other port to daisy-chain to the next Controller. Both ports work for the daisy-chain.

Finish the loop (Figure 34)
On the last stack, plug in the provided terminator to the last open RJ-45 port.

Completing Installation
1. Double check to ensure the battery system is securely mounted and level.
2. Double check to ensure all power connections are properly torqued.
3. Double check to ensure all communication cables are fully plugged in and seated.
4. Double check to ensure the Positive, Negative, and Ground terminals are all “Open” (not shorted) (i.e. Pos-to-Neg, Pos-to-Ground, Neg-to-Ground)

Programming and Commissioning
Make sure the SimpliPHI 6.6 BESS is OFF. (No LEDs on the batteries or Controller should be illuminated.)
Turn on the most stable energy source to the inverter and/or charge controller. This could be the connection to the grid or battery system. A stable grid connection is the most recommended. If required by the inverter, turn on the SimpliPHI 6.6 BESS (see step 5).
3. Turn on the inverter and/or charge controllers in the system.

Check the inverter settings.
 Make sure the settings match the charts.

Turn On Batteries
Turn on the SimpliPHI 6.6 BESS (hold down the power button) until all LEDs on the batteries and Controller are ON. Repeat for each stack.

EnergyTrak Programming and Commissioning
Let the batteries charge and move on to EnergyTrak installations or installations without an EnergyTrak gateway.
If utilizing a communications connected approved inverter with EnergyTrak gateway, follow the commissioning process outlined in the EnergyTrak manual. The commissioning is automated for ease.

Operation
Turn ON / OFF Battery Stack
ON: Press the button on the Controller for over 10 seconds, until all battery LEDs and Controller LEDs are illuminated.
OFF: Press the button on the Controller for over 10 seconds, until all battery LEDs are off. The Controller will turn OFF when the button is released.

The Controller LEDs show the current SOC of the battery stack:
1 LED = 0-25%, 
2 LED = 26-50%, 
3 LEDs = 51-75%, 
4 LEDs= 76-100%

If all of the LEDs are flashing, there is an issue. Please consult the Troubleshooting guide, the EnergyTrak app, or contact Technical Support.
The battery LED has 3 states:
ON: The battery is up, running, and healthy
OFF: The battery is off.
Blinking: There is an issue, please consult troubleshooting guide

Troubleshooting

Battery not providing voltage or power - Verify polarity on the cables is correct. +/+ and -/-.  Press and hold the On/Off button until the LED status light turns green

Battery indicating fault (flashing LED)
1. Press and hold the On/Off button until the LED status light turns off
2. Check EnergyTrak for the fault code

3. Call Technical Support (805-640-6700 x 1) ESSTech@basco.com

Appendix
    • Related Articles

    • Briggs and Stratton - Simpliphi 6.6

      BASCO Integration Guide Product Manual: www.bascodigital.com/assets/share/asset/a9krpstcso A maximum of 6 stacks can be connected in a single system. Per NFPA 855, a maximum of 40kWh in utility spaces or basements and 80kWh in garages our outdoor ...
    • Pylontech Pelio

      https://pylonwebs3.s3.amazonaws.com/upload/2024/09/25/RESS-Installation%20Manual-Pelio%205PMPA08-00124_20240925122854A042.pdf Set the 'StartV' for the voltage at which charging should initiate. Float V = 55.7 V Absorption V = 56.0 V Equalization V = ...
    • 08/14/25 Endur Energy Integration Status

      Endur Energy: Status Change EndurEnergy has been reclassified from "Certified" to "Proven" effective August 14th, 2025. Here is what that means, and what it does NOT mean: Do NOT tell customers Endur is no longer a partner. That is false. They will ...
    • Discover

      Notes You will need the Discover Lynk device to adapt the battery’s AEBus to CAN Bus for use with the Sol-Ark. The Lynk will need the proper adapter for the Sol-Ark’s pin configuration (Part number 950-0016-SLRK). Communications with this battery ...
    • Powersync

      Communications Installation and Setup Instructions 877-459-4591 support@powersyncenergy.com Manual Link: netorgft3957589.sharepoint.com/Shared Documents/Forms/AllItems.aspx?id=%2FShared Documents%2FLFP - Low Voltage Module%2FManuals%2FLFP-LV Module – ...